A repair desk answered eight of ten requests within one day. Two requests required parts that were not in stock and took three days to complete. The manager praised the speed of the first replies, but rejected a report saying that every repair had been completed within a day. She also refused a second claim that parts shortages always caused delay: one same-day repair used a part borrowed from another branch. The records showed what happened in these ten cases. They did not establish a rule for every future request. The desk used the same form for all ten requests and marked the date of first reply separately from the date of completion. The report did not record customer satisfaction or compare the branch with any other branch.
The next month, twenty requests were answered within a day, including four that needed parts. The report does not say whether those four parts were in stock, borrowed, or ordered.